Miele PDR 944 Installation Diagram

Taper
Installation Diagram
PDR944/544 EL
Electrically heated
en Installation Plan Commercial Tumble Dryers
fr Plan d’installation Sécheuses professionnelles
M.-Nr. 12 138 970
en - Contents
2
Installation notes ............................................................................................................. 3
Installation requirements ................................................................................................... 3
Floor anchoring ................................................................................................................. 3
Optional accessories......................................................................................................... 3
Communication box...................................................................................................... 3
XKM3200WLPLT ........................................................................................................ 3
Supply air, exhaust, and ventilation cross-sections.......................................................... 4
Supply air/exhaust air ................................................................................................... 4
Calculating the total length and diameter of a supply-air or exhaust pipe ................... 4
Substitute duct lengths................................................................................................. 5
Maximum permissible total ducting length................................................................... 5
Room ventilation opening for air intake from the setup room....................................... 6
Exhaust connection ...................................................................................................... 7
PDR944/544, electrically heated ................................................................................... 13
Dimensions........................................................................................................................ 13
Installation ......................................................................................................................... 14
Floor anchoring ................................................................................................................. 15
Technical data.................................................................................................................. 16
Possible voltage options ................................................................................................... 16
Exhaust air......................................................................................................................... 16
Supply air .......................................................................................................................... 16
Equipotential bonding ....................................................................................................... 16
APDR002 communication box (optional accessory)........................................................ 17
Machine data..................................................................................................................... 17
en - Installation notes
3
Installation requirements
Risk of injury or damage to property due to improper installation.
Incorrect installation of the tumble dryer can lead to personal injury or damage to prop-
erty.
It is recommended that installation and commissioning be accomplished by MieleSer-
vice or an authorized dealer.
The tumble dryer must be installed in accordance with all relevant regulations and stan-
dards. Observe all local codes.
The dryer must only be operated in a room that has sufficient ventilation and which is
frost-free.
The tumble dryer must not be installed behind a closeable door or a sliding door. The
maximum opening angle of the tumble dryer door must not be limited by objects or doors.
It must be possible to fully open the tumble dryer door at any time.
Floor anchoring
Miele generally recommends securing both of the tumble dryer’s front screw feet to the
floor with tensioning strips.
In the following cases, the tumble dryer must be secured to the floor with tensioning strips:
- when installing on a base
- on an offshore installation
Optional accessories
Only use genuine Miele spare parts and accessories with this machine.
Using parts or accessories from other manufacturers may void the warranty, and Miele
cannot accept liability.
Communication box
The optional communication box allows external hardware from Miele and other suppliers
to be connected to the MieleProfessional machine. External hardware includes e.g., peak-
load systems, pressure sensors, or an external vent flap.
The communication box is supplied with voltage by the Miele Professional machine.
The separately available set consists of the communication box and fasteners for installa-
tion on the machine or on the wall.
XKM3200WLPLT
The optional Miele communication module can be used to establish a data connection be-
tween a MieleProfessional machine and a data processor in accordance with the Ethernet
or WiFi standard.
This communication module fits into the communication slot which is a standard feature
on all machines. The communication module offers the option of intelligent app-based
communication with external systems. In addition, it can display detailed machine and pro-
gram status information.
en - Installation notes
4
This module forms the basis for wired communication with MieleMOVE.
It is not possible to integrate the machine into the “Miele@home” app for domestic in-
stallations.
The communication module is intended exclusively for commercial use and is supplied
with voltage directly via the Miele Professional machine. No additional power connection
is required. The Ethernet interface provided via the communication module complies with
SELV (safety extra low voltage) requirements in accordance with EN60950. Connected
external machines must also comply with SELV.
Supply air, exhaust, and ventilation cross-sections
Supply air/exhaust air
The tumble dryer may only be operated when the ducting has been connected properly
and the room is sufficiently ventilated.
Calculating the total length and diameter of a supply-air or exhaust pipe
The length of the required ductwork and the number and shape of the elbows are deter-
mined by the structural conditions on-site. In order to maximize the airflow efficiency, the
pipeline should be as short as possible and contain few or minimal elbows.
The exhaust ducting must not be made from flammable materials.
Otherwise there is a risk of fire.
Use only non-flammable materials for the exhaust ducting. All local regulations for
metallic ducting must be observed. Plastic must not be used for ventilation.
In upward exhaust ducting systems, a condensate drain must be fitted to the bottom. The
condensate must be drained via a water collection tray or a floor drain positioned in an ap-
propriate location.
If air is being directed from multiple appliances into a combined line (exceptional circum-
stances), a non-return device (non-return flap) must be installed in each separate line to
prevent backflow.
To make subsequent cleaning of the pipes easier, cleaning flaps should be fitted to elbows
wherever possible.
The on-site exhaust ducting and venting to the outdoors must be regularly checked for lint
deposits and cleaned if necessary.
en - Installation notes
5
Substitute duct lengths
Type of el-
bow
Type PDR
914/514
PDR
918/518
PDR
922/522
PDR
928/528
PDR
944/544
90° elbow r=2d 3' 7 5/16" (1.1m)
45° elbow r=2d 2' 3 9/16" (0.7m)
90° elbow r=d 6' 2 13/16" (1.9m)
45° elbow r=d 3' 7 5/16" (1.1m)
90° concertina duct el-
bow
r=2d 10' 6" (3.2m)
45° concertina duct el-
bow
r=2d 6' 6 3/4" (2m)
90° segmented elbow
(3welded seams)
r=2d 3' 11 1/4" (1.2m)
90° elbow, Westaflex
ducting
r=2d
r=4d
3' 11 1/4" (1.2m)
2' 11 7/16" (0.9m)
45° elbow, Westaflex
ducting
r=2d
r=4d
3' 3 3/8" (1m)
2' 7 1/2" (0.8m)
Non-return flap 39' 4 7/16"
(12m)
39' 4 7/16"
(12m)
22' 11 9/16"
(7m)
22' 11 9/16"
(7m)
21' 3 7/8"
(6.5m)
Table1
Maximum permissible total ducting length
Internal minimum pipe diameter
(metal ducting)
PDRx14 EL PDRx18 EL PDRx22 EL PDRx28 EL PDRx44 EL
5 7/8" (150mm) 62' 4 1/16"
(19m)
49' 2 9/16"
(15m)
39' 4 7/16"
(12m)
32' 9 11/16"
(10m)
32' 9 11/16"
(10m)
7 1/16" (180mm) 164' 1/2" (50m) 124' 8 1/16"
(38m)
101' 8 1/2"
(31m)
88' 7" (27m) 78' 8 7/8"
(24m)
7 7/8" (200mm) 278' 10 7/16"
(85m)
213' 3 1/16"
(65m)
173' 10 5/8"
(53m)
157' 5 3/4"
(48m)
130' (40m)
Permissible counter pressure in the ex-
haust ducting
0.05psi
(220Pa)
0.05psi
(340Pa)
0.05psi
(350Pa)
0.06psi
(410Pa)
0.04psi
(310Pa)
Table2
When connected to the vent ducting through the exhaust duct of a machine, particular
care must be taken to make sure the connection is secure and air-tight.
With complex ducting with many bends and additional components, or when several dif-
ferent machines are connected to a shared duct, it is recommended that a detailed
pipework calculation is carried out by a qualified specialist.
en - Installation notes
6
The vent ducting must not be channeled into a chimney or flue already in use for any gas-,
coal-, or oil-burning installation. The warm and moist exhaust air is to be conducted out-
side or to a suitable venting duct over the shortest path possible. The vent ducting must
be laid so that air flow is not hindered. To achieve this, use as few bends as possible along
with short pipelines and well-made connections and transitions checked for air-tightness.
No filters or grilles may be fitted in the vent ducting.
The end of the vent ducting leading out into the open should be protected against the ele-
ments, e.g., with a downward-facing 90° bend.
During tumble dryer operation, the room must be adequately ventilated.
Room ventilation opening for air intake from the setup room
The minimum dimension of the ventilation opening depends on the cross-section of the
vent duct.
Vent duct Minimum dimension for ventilation opening
  A A  
6"(150mm) - 277/16"²
(177cm²)
825/16"²
(531cm²)
101/4"
(260mm)
91/16"
(230mm)
- 6"
(150mm)
347/8"²
(225cm²)
1045/8"²
(675cm²)
115/8"
(295mm)
101/4"
(260mm)
71/16"(180mm) - 393/8"²
(254cm²)
1181/8"²
(762cm²)
123/8"
(315mm)
11"
(280mm)
- 71/16"
(180mm)
501/4"²
(324cm²)
15011/16"²
(972cm²)
14"
(355mm)
123/8"
(315mm)
77/8"(200mm) - 4811/16"²
(314cm²)
146"²
(942cm²)
133/4"
(350mm)
123/16"
(310mm)
- 77/8"
(200mm)
62"²
(400cm²)
186"²
(1,200cm²)
159/16"
(395mm)
133/4"
(350mm)
811/16"(220mm) - 587/8"²
(380cm²)
17611/16"²
(1,140cm²)
15"
(381mm)
1413/16"
(377mm)
- 811/16"
(220mm)
75"²
(484cm²)
2251/16"²
(1,452cm²)
1615/16"
(430mm)
151/16"
(382mm)
913/16"(250mm) - 761/8"²
(491cm²)
2285/16"²
(1,473cm²)
171/8"
(435mm)
153/16"
(385mm)
- 913/16"
(250mm)
967/8"²
(625cm²)
2905/8"²
(1,875cm²)
195/16"
(490mm)
171/8"
(435mm)
113/16"(300mm) - 1099/16"²
(707cm²)
3283/4"²
(2,121cm²)
201/2"
(520mm)
181/8"
(460mm)
- 113/16"
(300mm)
1391/2"²
(900cm²)
4181/2"²
(2,700cm²)
231/4"
(590mm)
201/2"
(520mm)
Table3
en - Installation notes
7
Exhaust connection
1 7/16" (37 mm)
Ø 5 15/16" (150 mm)
Ø 5 15/16" (151 mm)
Example1
Configuring vent ducting made from steel piping for the PDR914/514 tumble dryers:
L1, L2: each 9'10"(3m) steel piping
B1, B2: each 90° concertina pipe elbow (r = 2d)
B3: 90°elbow (r=d)
B3
L1
B1
B2L2
en - Installation notes
8
1.Total duct length
Steel pipe L1 = 9'10"(3.0m)
Steel pipe L2 = 9'10"(3.0m)
90° concertina pipe elbow
(r=2d)
B1 = 10'6"(3.2m)*
90° concertina pipe elbow
(r=2d)
B2 = 10'6"(3.2m)*
90°elbow (r=d) B3 = 6'3"(1.9m*)
Total duct length 46'11"(14.3m)
* Substitute duct lengths according to Table1
2.Duct diameter depending on total pipe length
For the calculated total pipe length of 46'11"(14.3m) for a PDR 914/514, a minimum duct
diameter of 6"(150mm) is specified for the exhaust ducting according to Table 2.
en - Installation notes
9
Example2
Common combined exhaust ducting for multiple appliances should only be considered as
a solution in exceptional cases.
Configuring combined exhaust ducting made from steel for the PDR 914/514 and PDR
918/518 series tumble dryers:
L1–L4 each 6'6"(2m) steel piping
B1–B3 each 90° concertina pipe elbow (r = 2d)
B4 45°elbow (r=2d)
B5 90°elbow (r=d)
If the exhaust from multiple appliances is to be ducted into a combined line, a non-return
device must be installed in each separate line to prevent backflow.
B2
L1
B1 B3
L2 L4 B5
B4
L3
PDR 914/514 PDR 918/518
en - Installation notes
10
1.Total pipe length PDR914/514
Steel pipe L1 = 6'6"(2.0m)
Steel pipe L2 = 6'6"(2.0m)
Steel pipe L4 = 6'6"(2.0m)
90° concertina pipe elbow
(r=2d)
B1 = 10'6"(3.2m)*
90° concertina pipe elbow
(r=2d)
B2 = 10'6"(3.2m)*
90°elbow (r=d) B5 = 6'3"(1.9m*)
Total duct length 46'11"(14.3m)
* Substitute pipe lengths according to Table1
2.Pipe diameter depending on total pipe length
Total pipe length=46'11"(14.3m)
Maximum permissible total pipe length 62'4"(19m)=Ø6"(150mm) internal pipe diame-
ter (see Table2)
3.Total pipe length PDR918/518
Steel pipe L3 = 6'6"(2.0m)
Steel pipe L4 = 6'6"(2.0m)
90° concertina pipe elbow
(r=2d)
B3 = 10'6"(3.2m)*
45°elbow (r=2d) B4 = 2'3"(0.7m)*
90°elbow (r=d) B5 = 6'2"(1.9m)*
Total duct length 32' 1 13/16" (9.8m)
* Substitute pipe lengths according to Table1
4.Pipe diameter depending on total pipe length
Total pipe length =32' 1 13/16" (9.8m) (PDR918/518)
Maximum permissible total pipe length 49'2"(15m)=Ø6"(150mm) internal pipe diame-
ter (see Table2)
5.Total duct diameter
According to Table3
Duct diameter PDR914/514 Ø6"(150mm)
=273/8"²(177cm²)
Duct diameter PDR918/518 Ø6"(150mm)
=273/8"²(177cm²)
Total cross sectionA = 5413/16"²(354cm²)
Total duct diameter = Ø811/16"(220mm)
en - Installation notes
11
Example3
Configuring exhaust ducting and a supply pipe made from steel for the PDR914/514 se-
ries tumble dryer:
L1, L2: each 6'6"(2.0m) steel piping
L3: 8'2"(2.5m) steel piping
B1, B2: 90° concertina pipe elbow for each
B3, B4: 90°elbow (r=d) for each
B2
L2
B3
L1
L3
B4
B1
1.Total duct length
Steel pipe L1 = 6'6"(2.0m)
Steel pipe L2 = 6'6"(2.0m)
Steel pipe L3 = 8'2"(2.5m)
90° concertina pipe elbow B1 = 10'6"(3.2m)*
90° concertina pipe elbow B2 = 10'6"(3.2m)*
90°elbow (r=d) B3 = 6'3"(1.9m*)
90°elbow (r=d) B4 = 6'3"(1.9m*)
Total duct length 54' 9 1/2" (16.7m)
* Substitute pipe lengths according to Table1
2.Pipe diameter depending on total pipe length
For the calculated total pipe length of 54'9"(16.7m) for a PDR914/514, a minimum pipe
diameter of 6"(150mm) is specified for the exhaust ducting and supply pipe according to
Table 2.
en - Installation notes
12
Configuring the room ventilation opening
Rooms in which rotary irons and tumble dryers are operated must have an induced
ventilation system (e.g., ventilation slots in windows and doors, wall openings with
grilles, or opened windows or skylights).
For example1
A duct diameter of 6"(150mm) was specified in example1. According to this duct diame-
ter, a room ventilation opening with a size of 17'5"(531cm) is required. The edge length is
91/16"(230mm) (see Table3).
For example2
A total duct diameter of 811/16"(220mm) was specified. According to this duct diameter,
a room ventilation opening with a size of 37'4"(1,140cm) is required. The edge length is
1413/16"(377mm) (see Table3).
For example3
Since in this case the tumble dryer is connected to a central air supply, additional ventila-
tion openings are not needed.
en - PDR944/544, electrically heated
13
Dimensions
uScrew foot
en - PDR944/544, electrically heated
14
Installation
aElectrical connection
bConnection for equipotential bonding
cExhaust duct
hConnection for communication module
iConnection for communication box
jCommunication box (optional)
For setting up a connection with external systems
en - PDR944/544, electrically heated
15
Floor anchoring
#Drill hole/anchor point
en - Technical data
16
Possible voltage options
208/240V60Hz3Ph
Power source 208/240V
60Hz
3Ph
Total amps 100.9A
Maximum fuse rating (time-delay fuse) 150A
Minimum current 126.1A
440/480V60Hz3Ph
Power source 440/480V
60Hz
3Ph
Total amps 54.6A
Maximum fuse rating (time-delay fuse) 70A
Minimum current 68.3A
Exhaust air
Airflow rate 990m³/h
Maximum permitted pressure loss 0.04psi (260Pa)
Maximum exhaust air temperature 175°F (80°C)
Maximum evaporation rate 83.7 lb/h (38kg/h)
Exhaust air connector on machine side 6" (DN150)
As relative humidity inside the exhaust ducting can be as high as 100%, suitable measures must be taken to prevent a backflow of
condensate into the machine.
Supply air
Standard connection: air intake from installation site
Recommended free air intake cross-section into the room:
(equivalent to 3 times the exhaust air cross-section of a machine).
146sq.in. (942cm²)
There must be sufficient air intake to the installation site to match the air outlet volume.
Alternative connection: air intake connection directly from outdoors
Connection sleeve on machine side (internal diameter) 6 5/16" (161mm)
Connection pipe provided on site (external diameter) 6 5/16" (160mm)
Removing the protective cover exposes live parts. For safety reasons, a pipe must be installed from the tumble dryer’s central fresh air
intake (over a minimum length of 35 7/16" (900mm)) and secured with 2screws.
Equipotential bonding
Connection with male thread 10×35mm
Washers and nuts M10
Accessories for equipotential bonding are not supplied and need to be ordered separately.
en - Technical data
17
APDR002 communication box (optional accessory)
Electrical connection ~ 200–240V, 50/60Hz
Net height 9 9/16" (243mm)
Net width 11 3/4" (298mm)
Net depth 3 3/4" (96mm)
Gross height (including packaging) 5 11/16" (145mm)
Gross width (including packaging) 11 1/2" (292mm)
Gross depth (including packaging) 23 7/16" (595mm)
Net weight 7.5lb (3.4kg)
Gross weight (including packaging) 8.274lb (3.75kg)
Machine data
Machine width, total 47 1/2" (1,206mm)
Machine height, total 64 9/16" (1,640mm)
Machine depth, total 54 1/2" (1,384mm)
Niche width 61" (1,550mm)
Minimum wall spacing (up to the back edge of the lid) 19 11/16" (500mm)
Packaging width 54 3/4" (1,390mm)
Packaging height 69 1/2" (1,766mm)
Packaging depth 58 1/16" (1,474mm)
Maximum gross volume 956gal (3,618.3L)
Maximum gross weight 774lb (337.4kg)
Maximum net weight 704lb (319.3kg)
Maximum floor load in operation 3,780N
Diameter of exhaust duct 5 7/8" (150mm)
Drum diameter 43 5/16" (1,100mm)
Diameter of drum opening 20 1/2" (520mm)
Drum depth 34 1/2" (876mm)
Drum volume 211gal (800L)
Door opening diameter 20 1/2" (520mm)
Maximum door opening angle 180°
Emission sound pressure level 63dB(A) re 20µPa
Sound power level 72dB(A)
Average heat dissipation rate into the room 4MJ/h
Permissible ambient temperature range during use 36-104°F (2–40°C)
fr - Table des matières
18
Consignes d'installation ................................................................................................. 19
Conditions d’installation.................................................................................................... 19
Ancrage au sol................................................................................................................... 19
Accessoires en option....................................................................................................... 19
Boîtier de communication............................................................................................. 19
XKM3200WLPLT ........................................................................................................ 19
Sections d’alimentation en air, d’évacuation et de ventilation.......................................... 20
Alimentation en air/évacuation d’air............................................................................ 20
Calcul de la longueur totale et du diamètre d’un tuyau d’évacuation d’air ou d’ali-
mentation en air ............................................................................................................ 20
Longueurs des conduites de substitution..................................................................... 21
Longueur totale admissible maximale de la conduite................................................... 21
Ouverture de ventilation de la pièce pour l’admission d’air provenant de la salle
d’installation.................................................................................................................. 22
Raccord d’évacuation d’air........................................................................................... 23
PDR944/544, chauffage électrique ............................................................................... 30
Dimensions........................................................................................................................ 30
Installation ......................................................................................................................... 31
Ancrage au sol................................................................................................................... 32
Caractéristiques techniques .......................................................................................... 33
Variantes de tension possibles.......................................................................................... 33
Évacuation d’air................................................................................................................. 33
Alimentation en air............................................................................................................. 33
Liaison équipotentielle....................................................................................................... 33
Boîtier de communication APDR002 (accessoire en option) ........................................... 34
Caractéristiques de l’appareil............................................................................................ 34
fr - Consignes d'installation
19
Conditions d’installation
Risque de blessure ou de dommage matériel en cas d'installation incorrecte.
Une installation incorrecte de la sècheuse peut entraîner des blessures ou des dom-
mages matériels.
Il est recommandé que l'installation et la mise en service soient effectuées par le service
Miele ou un revendeur agréé.
La sécheuse doit être installée conformément à toutes les réglementations et normes en
vigueur.
La sécheuse ne doit être utilisée que dans une pièce suffisamment ventilée et à l’abri du
gel.
La sècheuse ne doit pas être installée derrière une porte fermable ou une porte coulis-
sante. L'angle d'ouverture maximal de la porte de la sècheuse ne doit pas être limité par
des objets ou des portes. La porte de la sècheuse doit pouvoir être ouverte complètement
à tout moment.
Ancrage au sol
Miele recommande généralement de fixer au sol les deux pieds à visser à l’avant de la sé-
cheuse au moyen de bandes de tension.
Dans les situations suivantes, la sécheuse doit être fixée au sol au moyen des bandes de
tension:
- Installation de l’appareil sur un socle
- Installation de l’appareil en mer
Accessoires en option
N’utiliser que des accessoires et des pièces de rechange d’origine Miele avec cet appa-
reil.
Si des pièces de rechange ou des accessoires d’autres fabricants sont utilisés, la garan-
tie sera annulée, et Miele n’acceptera aucune responsabilité.
Boîtier de communication
Le boîtier de communication en option permet de raccorder le matériel externe de Miele et
d’autres fournisseurs à l’appareil MieleProfessional. Le matériel externe comprend, par
exemple, des systèmes de délestage, des capteurs de pression ou une soupape d’évacua-
tion externe.
Le boîtier de communication est fourni avec la tension réseau par l’appareil MieleProfes-
sional.
Le jeu disponible séparément comprend le boîtier de communication et les fixations pour
l’installation sur l’appareil ou sur le mur.
XKM3200WLPLT
Le module de communication Miele en option peut être utilisé pour établir une connexion
de données entre un appareil MieleProfessional et un système de traitement des données,
conformément à la norme Ethernet ou Wi-Fi.
fr - Consignes d'installation
20
Ce module de communication s’insère dans la fente de communication faisant partie de
l’équipement standard de tous les appareils. Le module de communication offre l’option
d’une communication intelligente basée sur une application avec des systèmes externes.
De plus, il peut afficher des informations détaillées sur l’état de l’appareil et du pro-
gramme.
Ce module constitue la base de la communication câblée avec MieleMOVE.
Il n’est pas possible d’intégrer l’appareil dans l’application «Miele@home» pour les ins-
tallations domestiques.
Le module de communication est destiné exclusivement à un usage de qualité profes-
sionnelle, et il est alimenté en tension réseau directement par l’appareil MieleProfessio-
nal. Aucun raccordement électrique supplémentaire n’est nécessaire. L’interface Ethernet
fournie par le module de communication est conforme aux exigences de la TBTS (Très
basse tension de sécurité) selon la norme EN60950. Les appareils externes branchés
doivent également respecter la TBTS.
Sections d’alimentation en air, d’évacuation et de ventilation
Alimentation en air/évacuation d’air
La sécheuse ne peut être utilisée que lorsque les conduites d’évacuation d’air ont été cor-
rectement raccordées et que la pièce est suffisamment ventilée.
Calcul de la longueur totale et du diamètre d’un tuyau d’évacuation d’air ou d’alimen-
tation en air
La longueur de la tuyauterie requise, ainsi que le nombre et la forme des coudes sont dé-
terminés par les conditions structurelles sur place. Afin de optimiser l’efficacité de la circu-
lation de l’air, la tuyauterie doit être aussi courte que possible et contenir peu ou pas de
coudes.
La conduite d’évacuation d’air ne doit pas être fabriquée à partir de matériaux in-
flammables.
Sinon, il existe un risque d’incendie.
Utiliser uniquement des matériaux non inflammables pour la conduite d’évacuation d’air.
Toutes les réglementations locales relatives aux conduites d’évacuation métalliques
doivent être respectées. Le plastique ne doit pas être utilisé pour la ventilation.
Dans les systèmes de conduite d’évacuation d’air inclinés vers le haut, une évacuation du
condensat doit être installée dans la partie inférieure. Le condensat doit être évacué via un
bac de récupération d’eau ou d’une vidange au sol placé à un endroit approprié.
Si l’air est dirigé depuis plusieurs appareils vers une ligne combinée (circonstances excep-
tionnelles), un dispositif anti-retour (clapet anti-retour) doit être installé sur chaque ligne
afin d’éviter tout reflux.
Pour faciliter grandement le nettoyage ultérieur des conduites, il convient d’installer, dans
la mesure du possible, des clapets de nettoyage sur les coudes.
Les conduites d’évacuation d’air et la ventilation vers l’extérieur sur place doivent être ré-
gulièrement contrôlées pour vérifier l’absence de dépôts de peluches, puis nettoyées si
nécessaire.
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36

Miele PDR 944 Installation Diagram

Taper
Installation Diagram

dans d''autres langues