DESCRIPTION AND OPERATION
The Lighting Integrator lighting control panel with emergency shunt operation is designed to allow the normal control of the emergency
lighting for day to day operation of the building. The panel is configured to guarantee that the emergency lighting served by the panel
will always turn on upon loss of normal power regardless of the controlled state of the relays in the panel.
Under normal operation of the lighting control panel, the SPST relays will control the lighting based on the sequence of operation
designed for the panel. This could include schedules, overrides from low voltage wall switches, and daylight or occupancy sensors
connected to the panel. Normal control is allowed because the contacts of the shunt contactors are held open by the normal power
sense circuit.
When the normal power sense circuit stops supplying voltage (power outage), the normally closed contacts on the shunt contactors
close thus bypassing the switching action of the SPST relays.
When normal power is restored, the normal power sense circuit will once again supply power to open, and hold open, the contacts on
the shunt contactors thus restoring the normal control operation of the Lighting Integrator panel.
See the wiring diagram on the next page.
For an overview of the entire system and the documentation forms, refer to the Lighting Integrator Installation and Operation Manual. If
you have any questions, call our Service Team.
INSTALLING THE EMERGENCY RELAY PANEL
Lighting Integrator lighting control panels ordered with the Emergency Shunt option are shipped completely assembled and should
not require disassembly in the field for proper installation. Panels equipped with normal and emergency relays require that they be
separated by a metal barrier. Install the supplied barrier(s) in the appropriate location(s) as shown on the detail drawing in the project
submittal documentation. Refer to the Lighting Integrator Panel Installation Instructions shipped with your panel for other installation
information.
1. Mount the panel enclosure to the wall using hardware (not supplied) capable of supporting a minimum of 100 pounds.
2. Mount the interior into the enclosure using the supplied hardware.
3. Connect the panel’s power supply to a source of 120 or 277 volt power. It is not necessary for this power supply to be on
emergency power for the emergency shunt operation to work properly.
4. Connect the branch circuit feed wires from the emergency panel to the LINE side terminal on each relay. Connect the LOAD
side of each relay to the corresponding load circuit. Care should be taken to make sure the factory wire connections to the relays
remain connected as shipped.
5. Connect the normal power sense leads from the shunt contactors in the relay panel to a dedicated 20 amp circuit from the lighting
panel serving the same section of the building as the Lighting Integrator emergency control panel. Note that these connections are
voltage sensitive and ensure that all voltages match.
6. Test the shunt operation of the panel by cycling the 20 amp breaker feeding the normal power sense circuit in the Lighting
Integrator panel. An audible noise should be noted when power is applied to the normal power sense circuit. This is the sound
of the shunt contactors opening to allow normal operation of the relays. Likewise, a an audible noise should be noted when the
normal power sense circuit is turned off (this simulates a power failure) and the contactors close, thus shunting the contacts of the
relays and turning on all the emergency lighting controlled by this panel.
WARNING: TURN THE POWER OFF AT THE
CIRCUIT BREAKER BEFORE WIRING.
800.879.8585
www.legrand.us/wattstopper
No. 28431 – 1/19 rev. 1
© Copyright 2019 Legrand All Rights Reserved.
© Copyright 2019 Tous droits réservés Legrand.
© Copyright 2019 Legrand Todos los derechos reservados.
Wattstopper warranties its products to be free
of defects in materials and workmanship for a
period of five (5) years. There are no obligations
or liabilities on the part of Wattstopper for
consequential damages arising out of, or in
connection with, the use or performance of this
product or other indirect damages with respect
to loss of property, revenue or profit, or cost of
removal, installation or reinstallation.
Wattstopper garantit que ses produits sont
exempts de défauts de matériaux et de fabrication
pour une période de cinq (5) ans. Wattstopper
ne peut être tenu responsable de tout dommage
consécutif causé par ou lié à l’utilisation ou
à la performance de ce produit ou tout autre
dommage indirect lié à la perte de propriété, de
revenus, ou de profits, ou aux coûts d’enlèvement,
d’installation ou de réinstallation.
Wattstopper garantiza que sus productos
están libres de defectos en materiales y mano
de obra por un período de cinco (5) años. No
existen obligaciones ni responsabilidades por
parte de Wattstopper por daños consecuentes
que se deriven o estén relacionados con el
uso o el rendimiento de este producto u otros
daños indirectos con respecto a la pérdida
de propiedad, renta o ganancias, o al costo
de extracción, instalación o reinstalación.
WARRANTY INFORMATION INFORMATIONS RELATIVES À LA GARANTIE INFORMACIÓN DE LA GARANTÍA
Relay
Emergency Lighting Ci
rcuit
Emergency
Light Fixture
Normal Power
Sensing Circuit
Contactor
NC
Coil
Line
N
N
Line
BLUE wires: Contractor Wiring
RED wires: Factory Wire
WIRE CODE