Comissioning
WARNING
Before carrying out any work, ensure local and site procedures are
followed. Ensure that the associated control panel is inhibited to
prevent false alarms.
The following procedure should be followed carefully and only performed by
suitably trained personnel.
1. Ensure the detector is wired correctly.
2. Ensure that the correct sensor cartridge is fitted. (If the
cartridge has not been stored at room temperature, allow one
hour for equilibration.)
3. Ensure the on/off switch on the bottom of the mounting
bracket assembly is in the on position.
4. Apply power to the system.
5. After the startup routine, the detector will display the normal
operating mode.
6. Perform a leak test to ensure all connections are secure.
7. ‘Waiting…’ will be displayed on booting time.
8. Allow the detector to stabilize until the ‘Warm-up’ message
is no longer displayed after booting. The maximum warm-up
time is dependent on sensor type. Refer to individual cartridge
datasheets. Warm-up times are typically much faster.
9. Ensure the correct ID code is selected in Set-up -> alarm
menu
10. If this is a first-time startup, the “Detect New Cartridge ~”
message could be displayed. Press the ‘O’ button to clear the
message.
Mise en service
ATTENTION
Avant de réaliser tout travail, s’assurer que les procédures locales
et de chantier sont suivi. Assurez-vous que le panneau de com-
mande associé est empêché de prévenir les fausses alarmes.
La procédure suivante doit être suivie attentivement et ne doit être effec-
tuée que par personnel convenablement formé.
1. Assurez-vous que le détecteur est câblé correctement.
2. Assurez-vous que la bonne cartouche de capteur est installée.
(Si la la cartouche n’a pas été conservée à la température
ambiante, laissez-la heure d’équilibration.)