Installation Class 1640
Installation
This section provides instructions for the following NQ panelboard and QONQ load
center procedures:
•Interior Mounting for Square D Brand Enclosures, page 7.
•Neutral Bonding Strap/Cable Installation, page 9.
•QO and QOB Circuit Breaker Installation and Removal, page 13.
•Circuit Breaker Reset Instructions, page 15.
•Deadfront Preparation, page 16.
Interior Mounting for Square D Brand Enclosures
A separate standards publication, titled “General Instructions for Proper Installation,
Operation, and Maintenance of Panelboards Rated 600 Volts or Less” (NEMA PB1.1),
has been provided with this equipment. Familiarize yourself with the content of this
document before proceeding with any of the following procedures.
If you did not receive a copy of this document, or if you have any questions regarding
this equipment, contact your local distributor or Schneider Electric representative.
NOTICE
HAZARD OF EQUIPMENT DAMAGE DUE TO LOOSE CONNECTIONS
• Ensure all connections are properly tightened.
• Refer to the torque information label provided on the panelboard before
tightening the connections.
Failure to follow these instructions can result in equipment damage.
To properly mount and install the NQ panelboard or QONQ load center interior, please
refer to the NEMA PB 1.1 standards publication, and follow the instructions below for
either Surface Mounting (Enclosure Mounted on Wall), page 7 or Flush Mounting
(Enclosure Recessed in Wall), page 8.
Surface Mounting (Enclosure Mounted on Wall)
1. Mount the enclosure as instructed in the NEMA PB 1.1 standards publication.
2. Remove the deadfront from the deadfront brackets.
3. Install the interior as described below:
a. Set the interior on the enclosure studs. An elevating screw is not required
(See Interior Mounting for Square D Brand Enclosures, page 7).
b. Tighten the Keps nuts against the interior side rails until the rails are against
the back of the enclosure.
4. Based on the application and adopted installation code, Neutral Bonding Strap
and Line Side Barrier may be required. See the Neutral Bonding Strap/Cable
Installation, page 9 and Appendix 2: Accessory Kits, page 35.
5. Apply equipment labels (located in the bag assembly) as directed by the
instructions on the back of the equipment label sheet. Please consult local codes
and standards.
80043-712-06 7