p5
Important:
From the version 2.02 of the TPIs it is possible to access the configuration of
the instruments of the bus directly from the master.
In this case first connect the instrument defined as master (TPIs or TPIvM),
programme it as master if it is a TPIs and click on «communication through the
master» and then «add or remove some devices».
The software will then take up all the instruments present on the bus and read
their configuration one by one.
For each instrument detected, the SlimSet will request its position on the archi-
tecture. This position can be determined by a specific blinking of the green led
of the concerned instrument (morse code blinking: twice on, once off).
3) Then programme each of the instruments, as well as the links between ins-
truments:
for each of the outputs of the output modules (TPIs 4R, TPIs 2A/4A ...) you
must define the converter associated with this output, as well as the measure
associated with this output.
4) Then transfer the programming of all the instruments of the bus.
Important :
From the version 2.02 of the TPIs, it is possible to transfer the programming of
the TPIs directly from the master.
For this purpose, connect yourself on the master and click on «communication
with the devices» and then «communication through the master» and then «send
the configuration of all devices».
Then transfer the programming of the master.
5) Then validate the bus. For this purpose connect yourself on the master, click on
«validate network».
This will record the configuration of the bus in order to point out any error (loss of
a module for example).
The network must always be validated after adding / removing an instrument and
after the modification of all the links between instruments.
3. DIMENSIONS, MOUNTING
Dimensions:............................................ 7.2 x 114 x 114 mm
Housing: ................................................. self-extinguishing of PBT
Terminals: ............................................... screwed connections (2.5mm²,
flexible or rigid)
Screw thread .......................................... M3
Max. tightening torque............................ 0.5Nm / 4.5in.lbs
Min. solid/stranded conductor section .... 0.2mm2 / 26 AWG
Max. solid/stranded conductor section ... 2.5mm2 / 14 AWG
Protection: .............................................. case / terminals: IP20
• Mounting in switchbox: latching on symmetrical DIN rail, with footing for
the distribution of the 24Vdc power supply and the communication signals.
Instructions for assembling on 35mm DIN rail according to EN 60715
Assembling of
the footings
on the rail
BEWARE:
The
polarization
tongue is at
the bottom.
Assembling of
the footings
before mounting
on DIN rail