BCK SF 26CT • Setup Guide
This setup guide contains installation information about the BCK SF 26CT back-can. When installed and assembled together with
the DAK SF 26CT, they become a fully functional SF 26CT SoundField
®
XD 2-way speaker.
The complete assembly can be installed by a single-trade installation or a multi-trade installation procedure (see the SF 26CT
User Guide, available at www.extron.com, for details). The entire assembly is plenum rated.
WARNING: Potential risk of severe injury. Installation and service must be performed by authorized personnel only.
AVERTISSEMENT: Risque potentiel de blessure grave ou de mort. L’installation et l’entretien doivent être effectués
par le personnel autorisé uniquement.
NOTE: Installation of conduit and conduit adapters must conform to all applicable building codes and local ordinances.
1
Preparing the Installation Location
1. Power down all attached devices before proceeding.
2. Using the provided cutout template for the outline, cut
a hole for the BCK SF 26CT in the ceiling tile, as
described below.
NOTE: For hard ceiling installations:
Skip steps a through e and just use the
template to cut a hole in the ceiling.
a. Remove the ceiling tile, and draw diagonal lines
across it from opposite corners to locate its center.
Mark the intersection where the lines cross.
b. Position the center hole of the cutout template
directly over the center of the tile, marked in
step2a.
c. Trace a circle on the ceiling tile around the cutout
template.
d. Cut out the circle traced in the ceiling tile.
e. Replace the ceiling tile in the ceiling.
3. Attach two V-rails and one C-ring above the hole cut
in step 2, as described below.
NOTE: For hard ceiling installations:
• Fold one C-ring assembly in half and insert it
through the hole in the ceiling.
• Unfold the C-ring and center it over the hole
with the at side down.
• V-rails are not needed.
a. Assemble two V-rail half sections by fitting the tab
of one end into the slot of the other end. Open the
V-rail until it locks together (see figure 1). Repeat
this procedure for the other V-rail.
b. For ease of access, Remove a ceiling tile adjacent
to the cut tile.
c. Place both assembled V-rails on the cut ceiling tile
and position them equally on either side of the hole.
The ends of the V-rails go over the ceiling grid (see
figure 2, on next page).
Installing the BCK SF 26CT into a Suspended Ceiling
Figure 1. Assembling the V-rails