STEP • ÉTAPE
4
STEP • ÉTAPE
5
WWW.PYLEX.COM
42’’
RE-INSTALL THE
TRIANGLE (H) PART ON
TOP OF PIECE (B)
REMETTRE LE
TRIANGLE (H) SUR LE
HAUT DE LA PIECE (B)
1
2
SCREW IN THE REMAINING 6" IN
NOT MECHANICALLY MOVED
GROUND UNTIL THE POST REMAIN
36" ABOVE THE GROUND
VOUS DEVEZ VISSER DANS 6"
DE SOL NON REMANIER JUSQU’À
CE QU’IL RESTE 36" HORS SOL
36"36"
BB
36’’
CONTINUE TO SCREW IN 6" AND
REMOVE THE GROUND EACH TIME UNTIL
THE PIECE (B) IS 42" ABOVE GROUND LEVEL
** THEN STOP TO REMOVE THE GROUND **
CONTINUER DE VISSER 6" ET ENLEVER LA
TERRE À CHAQUE FOIS JUSQU’À CE QUE
LA PIÈCE (B) SOIT À 42" AU DESSUS DU
NIVEAU DU SOL
** ARRÊTER D’ENVELER LA TERRE**
5
G1