Instructions
36" Island Chimney Vent Hood
ZV925
49-80329-4
2
Installation Instructions
WARNING: TO REDUCE THE RISK OF FIRE,
ELECTRICAL SHOCK OR INJURY, OBSERVE THE FOLLOWING:
A. Use this unit only in the manner intended by the
manufacturer. If you have any questions, contact the
manufacturer.
B. Before servicing or cleaning unit, switch power off at the
service panel and lock service panel to prevent power from
being switched on accidentally. If the service panel cannot
be locked, fasten a tag or prominent warning label to the
panel.
AVERTISSEMENT :
POUR RÉDUIRE LE RISQUE D’INCENDIE, DE CHOC
ÉLECTRIQUE OU DE BLESSURES, IL FAUT OBSERVER LES
REGLES SUIVANTES :
A. Utilisez cet appareil uniquement de la maniére prévue par
le fabricant. En cas de question, consultez le fabricant.
B. Avant toute intervention ou nettoyage, coupez
l’alimentation électrique au disjoncteur et verrouiller
le panneau du disjoncteur pour éviter la mise sous
tension accidentelle. S’il n’est pas possible de verrouiller
le panneau du disjoncteur, attachez un placard ou une
étiquette trés visible au panneau.
For general ventilating use only. Do not use to exhaust
hazardous or explosive materials or vapors.
Structural framing, installation work and electrical wiring
must be done by qualified person(s) in accordance with
all applicable codes and standards, including fire-rated
construction.
Sufficient air is needed for proper combustion and
exhausting of gases through the flue (chimney) of fuel
burning equipment to prevent back drafting. Follow the
heating equipment manufacturer’s guidelines and safety
standards such as those published by the National Fire
Protection Association (NFPA), and the American Society
for Heating, Refrigeration and Air Conditioning Engineers
(ASHRAE), and the local code authorities. When applicable,
install any makeup (replacement) air system in accordance
with local building code requirements. Visit GEAppliances.
com for available makeup air solutions.
Local codes vary. Installation of electrical connections
and grounding must comply with applicable codes. In
the absence of local codes, the vent should be installed
in accordance with National Electrical Code ANSI/NFPA
70-1990 or latest edition.
CAUTION: To reduce risk of fire and to properly
exhaust air, be sure to duct air outside. Do not vent exhaust
air into spaces within walls or ceilings or into attics, crawl
spaces or garages.
PRUDENCE : Il faut prendre soin d’installer
un conduit vers l’extérieur pour réduire le risque d’incendie
et pouvoir évacuer l’air correctement. Il ne faut pas évacuer
l’air dans l’espace entre les parois d’un mur, un plafond ou un
grenier, un espace sanitaire ou un garage.
BEFORE YOU BEGIN
Read these instructions completely and
carefully.
IMPORTANT Save these instructions for local
inspector’s use.
IMPORTANTObserve all governing codes and
ordinances.
Note to Installer – Be sure to leave these instructions
with the Consumer.
Note to Consumer – Keep these instructions for
future reference.
Skill Level – Installation of this vent hood requires
basic mechanical and electrical skills.
Completion time – 1 to 3 hours.
Proper installation is the responsibility of the installer.
Product failure due to improper installation is not
covered under the Warranty.
CAUTION:
Due to the weight and size of these vent hoods and
to reduce the risk of personal injury or damage to the
product, THREE PEOPLE ARE REQUIRED FOR PROPER
INSTALLATION.
PRUDENCE :
À cause du poids et des dimensions du ces hottes et
pour réduire les risques de blessures ou de dommages
du produit, IL FAUT TROIS PERSONNES POUR FAIRE
UNE INSTALLATION CORRECTE.
WARNING:
To reduce the risk of fire or electrical shock, do not use
this range hood with any external solid-state speed
control device. Any such alteration from original factory
wiring could result in damage to the unit and/or create
an electrical safety hazard.
AVERTISSEMENT :
Pour réduire le risque d’incendie ou de choc électrique,
il ne faut pas utiliser cette hotte avec un régulateur
de vitesse électronique externe. Toute modification de
ce type du branchement d’usine peute endommager
l’appareil ou créer un risque de choc électrique.
TO REDUCE THE RISK OF FIRE, USE ONLY METAL
DUCTWORK.
3
Design Information
PRODUCT DIMENSIONS
CONTENTS
Design Information
Product Dimensions ...............................................................................3
Advance Planning
Advance Planning ..................................................................................4
Power Supply ...........................................................................................4
Duct Fittings ............................................................................................ 5
Installation Preparation
Installation Height .................................................................................6
Tools and Materials Required ...........................................................7
Remove the Packaging .......................................................................7
Parts Provided ..........................................................................................8
Installation Preparation
Construct Ceiling Support ...........................................................9–11
IQVWDOODWLRQ,QVWUXFWLRQV³9HQWHGWRWKH2XWVLGH
Step 1, Mount Template ...................................................................12
Step 2, Adjust Frame Height...........................................................12
Step 3, Cut Duct to Length for Vented Installation ............13
Step 4, Install the Support Frame ................................................13
Step 5, Install Hood Attachment Screws .................................13
Step 6, Mount the Hood onto the Support .............................14
Step 7, Connect Cables .....................................................................14
Step 8, Connect Electrical ................................................................15
Step 9, Prepare the Duct Covers ..................................................16
Step 10, Install Upper Duct Cover ...............................................16
Step 11, Install Lower Duct Cover ...............................................17
Step 12, Install Duct Cover Trim ...................................................17
Step 13, Install Metal Filter ..............................................................17
Step 14, Finalize Installation ...........................................................17
IQVWDOODWLRQ,QVWUXFWLRQV³5HFLUFXODWLQJ
Step 1, Mount Template ...................................................................18
Step 2, Adjust Frame Height...........................................................18
Step 3, Install Air Deflector, Cut Duct
for Recirculating Operation ............................................19
Step 4, Install Upper Support Frame ..........................................19
Step 5, Install Lower Structure to Upper Structure ............20
Step 6, Install Blower/Motor ...........................................................20
Step 7, Install Hood Attachment Screws .................................21
Step 8, Mount the Hood onto the Support .............................21
Step 9, Connect Cables .....................................................................21
Step 10, Connect Electrical .............................................................22
Step 11, Prepare the Duct Covers ...............................................23
Step 12, Install Upper Duct Cover ...............................................23
Step 13, Install Lower Duct Cover ...............................................24
Step 14, Install Duct Cover Trim ...................................................24
Step 15, Install Filters .........................................................................25
Step 16, Finalize Installation ...........................................................25
These vent hoods are supplied with a support frame
for ceiling heights of 7'-11" to 10'-1".
Decorative duct covers conceal the ductwork running
from the top of the hood to the ceiling.
ZX92510 accessory is available for ceiling heights of
9'-1" to 10’-1".
27 9/16"
3 1/4"
35 7/8"
*Height
to
Ceiling
* The supplied duct cover fits 7'-11" to 9' ceiling
heights. For 9'-1" to 10'-1" ceilings, order ZX92510.
NOTE: Installation height should be measured from
the cooking surface to the bottom of the outer glass
portion of the hood.
This hood must be installed 24" min. and 30" max.
above the cooking surface. The cooking surface
should be at least 36" above the floor.
This hood may be vented to the outdoors, or it can be
installed for recirculating operation.
This hood can be installed over any Monogram
electric or gas cooktop. It cannot be installed over a
Monogram Professional cooktop or range.
2 3/4"
*Height
to
ceiling
27 9/16"
35 7/8"
24"min.*
30"max.*
36"min.
* Exact installation
height depends
on ceiling height.
Advance Planning
ADVANCE PLANNING
Ductwork Planning
These vent hoods are equipped for 8" round
ductwork.
Determine the exact location of the vent hood.
Plan the route for venting exhaust to the outdoors.
Use the shortest and straightest duct route
possible. For satisfactory performance, duct run
should not exceed 100 ft. equivalent length for any
duct configurations.
Refer to “Duct Fittings” chart to compute the
maximum permissible length for duct runs to the
outdoors.
Use rigid metal ductwork only.
Install a roof cap with damper at the exterior
opening. Order the cap and any transitions needed
in advance.
When applicable, install any makeup (replacement)
air system in accordance with local building code
requirements. Visit GEAppliances.com for available
makeup air solutions.
Ceiling Framing for Adequate Support
These vent hoods are heavy. Adequate structural
support must be provided. The ceiling structure
must be capable of supporting the weight of the
hood and any inadvertent user contact loads
(approximately 200 pounds). The hood support
frame will be supported by 2 x 4 cross framing.
Installation will be easier if the vent hood is
installed before the cooktop or countertop below is
installed.
Accessory Duct Cover
All models are shipped with a duct cover for ceiling
heights of 7'-11" to 9'.
POWER SUPPLY
IMPORTANT - (Please read carefully)
WARNING:
FOR PERSONAL SAFETY, THIS APPLIANCE MUST BE
PROPERLY GROUNDED.
ATTENTION : POUR DES RAISONS DE
SÉCURITÉ, CET APPAREIL DOIT ÊTRE CORRECTEMENT
MIS À LA TERRE.
Remove house fuse or open circuit breaker before
beginning installation.
Do not use an extension cord or adapter plug with
this appliance. Follow National electrical codes or
prevailing local codes and ordinances.
Electrical Supply
This vent hood must be supplied with 120V, 60Hz,
and connected to an individual, properly grounded
branch circuit, and protected by a 15 or 20 amp
circuit breaker or time delay fuse.
• Wiring must be 2 wire with ground.
If the electrical supply does not meet the above
requirements, call a licensed electrician before
proceeding.
Route house wiring in the ceiling, as close to the
installation location as possible. Allow additional
length from ceiling joists to reach the junction
box on the bottom of the hood support frame.
Connect the wiring to the house wiring in
accordance with local codes.
Grounding Instructions
The grounding conductor must be connected to
a ground metal, permanent wiring system, or an
equipment-grounding terminal or lead on the hood.
WARNING: The improper connection of
equipment-grounding conductor can result in a risk
of electric shock. Check with a qualified electrician
or service representative if you are in doubt
whether the appliance is properly grounded.
AVERTISSEMENT :
Le mauvais branchement du fil de mise à la terre
peut causer un choc électrique. En cas de doute,
consultez un électricien qualifié ou un technicien
pour déterminer si l’appareil est à la terre.
4
ZX92510 accessory 36-3/4"duct cover is
available to reach 9'-1"to 10'-1" ceiling heights.
The accessory should be ordered with the hood
and be on site before final framing and wall
finishing.
5
DUCT FITTINGS
This Hood Must Use an
8d Round Duct. It Can
Transition to a
3-1/4d x 12d Duct.
Use this chart to compute
maximum permissible lengths for
duct runs to outdoors.
NOTE: Do not exceed maximum
permissible equivalent lengths!
Maximum duct length:
100 foot for range hoods.
Flexible ducting:
If flexible metal ducting is used,
all the equivalent feet values in
the table should be doubled.
The flexible metal duct should
be straight and smooth and
extended as much as possible.
DO NOT use flexible plastic
ducting.
NOTE: Any home ventilation
system, such as a ventilation
hood, may interrupt the proper
flow of combustion air and
exhaust required by fireplaces, gas
furnaces, gas water heaters and
other naturally vented systems.
To minimize the chance of
interruption of such naturally
vented systems, follow the
heating equipment manufacturer’s
guidelines and safety standards
such as those published by NFPA
and ASHRAE. When applicable,
install any makeup (replacement)
air system in accordance with local
building code requirements. Visit
GEAppliances.com for available
makeup air solutions.
Total
Equivalent Quantity Equivalent
Duct Piece Dimensions Length* Used Length
Round, 1 ft.
straight (per foot
length)
3-1/4" x 12" 1 ft.
straight (per foot
length)
90° elbow
17 ft.
45° elbow
10 ft.
ø[
90° elbow 43 ft.
3-1/4" x 12"
45° elbow 26 ft.
3-1/4" x 12"
90° flat elbow 102 ft.
8" round to
3-1/4" x 12" transition 2 ft.
3-1/4" x 12" to 8"
round transition 5 ft.
8" round
to 3-1/4" x 12"
transition 90° elbow 6 ft.
3-1/4" x 12" to 8" round
round transition 90° elbow 13 ft.
Round
wall cap
with damper 32 ft.
3-1/4" x 12" wall cap
with damper 75 ft.
Round
roof cap 44 ft.
Advance Planning
Total Duct Run
* Actual length of straight duct plus duct fitting
equivalent. Equivalent length of duct pieces are
based on actual tests conducted by GE Evaluation
Engineering and reflect requirements for good
venting performance with any ventilation hood.
DETERMINE INSTALLATION HEIGHT
Decorative duct covers are provided to conceal the
ductwork running to the ceiling.
This hood can be installed for recirculating
operation. No kits required.
The hood installation height, from the cooking
surface to the bottom of the hood, depends upon
ceiling height.
For optimum performance, the hood must be 24"
min. and 30" max. above the cooking surface.
Use the chart on this page to accurately determine
installation height and support frame adjustment,
and to select the correct size top trim piece (A, B, C
or D).
ZX92510 Accessory Duct cover includes a 36-3/4"
long duct cover and 3 sets of duct cover top trim
pieces labeled E, F, G.
Possible Hood Mounting
Ceiling Installation Frame Trim Piece
Height Height (inches) Height (inches) Needed
7'-11" 26 30 1/2 A
8'
27 30 1/2 A
8'-1" 24 34 1/2 B
8'-1" 28 30 1/2 A
8'-2" 25 34 1/2 B
8'-2" 29 30 1/2 A
8'-3" 26 34 1/2 B
8'-3" 30 30 1/2 A
8'-4" 27 34 1/2 B
8'-5" 24 38 1/2 C
8'-5" 28 34 1/2 B
8'-6" 25 38 1/2 C
8'-6" 29 34 1/2 B
8'-7" 26 38 1/2 C
8'-7" 30 34 1/2 B
8'-8" 27 38 1/2 C
8'-9" 24 42 1/2 D
8'-9" 28 38 1/2 C
8'-10" 25 42 1/2 D
8'-10" 29 38 1/2 C
8'-11" 26 42 1/2 D
8'-11" 30 38 1/2 C
9' 27 42 1/2 D
ZX92510 Accessory Duct Cover
9'-1" 24 46 1/2 E
9'-1"d 28 42 1/2 D
9'-2" 25 46 1/2 E
9'-2" 29 42 1/2 D
9'-3" 26 46 1/2 E
9'-3" 30 42 1/2 D
9'-4" 27 46 1/2 E
9'-5" 24 50 1/2 F
9'-5" 28 46 1/2 E
9'-6" 25 50 1/2 F
9'-6" 29 46 1/2 E
9'-7" 26 50 1/2 F
9'-7" 30 46 1/2 E
9'-8" 27 50 1/2 F
9'-9" 24 54 1/2 G
9'-9" 28 50 1/2 F
9'-10" 25 54 1/2 G
9'-10" 29 50 1/2 F
9'-11" 26 54 1/2 G
9'-11" 30 50 1/2 F
10' 27 54 1/2 G
10'-1" 28 54 1/2 G
6
Installation Preparation
D
C
B
A
7
Installation Preparation
TOOLS AND MATERIALS REQUIRED
(NOT SUPPLIED)
Pencil and tape measure
Pliers
120V 60Hz. 15 or 20 Amp,
2-wire with ground. properly
grounded branch circuit.
Key hole saw
Wire cutter/stripper
Step ladder
Metal snips
Saber saw
or sawsall
Wire nuts
Phillips and
flat blade
screwdrivers
Strain relief for
junction cover.
Spirit level
Flashlight
Safety glasses
8" round metal
duct, length to
suit installation.
Duct tape
3/8" swivel
socket or pivoting
hex socket with 6"
extensions
Carpenter’s square
REMOVE THE PACKAGING
CAUTION: LIFT THE HOOD OUT OF THE
BOX BY THE CENTER METAL PORTION. DO NOT LIFT
BY THE GLASS SIDES.
PRUDENCE : LEVEZ LA HOTTE À
L’EXTÉRIEUR DE LA BOÎTE PAR LA PORTION MÉTAL
CENTRAL. NE LEVEZ PAS PAR LES CÔTÉS DE VERRE.
CAUTION: Wear gloves to protect
against sharp edges.
PRUDENCE : Portez des gants pour
éviter les blessures causées par les tranchants.
Grasp the hood by the metal insert in the center
and lift straight up and out of the box.
Remove and properly discard the plastic wrapping.
Remove parts box, duct covers and other
packaging.
Hammer
Electric or battery-operated
drill and 3/16" bits, Phillips and
flat blade screwdriver bits.
Installation Preparation
PARTS PROVIDED
Locate the parts packed with the hood.
HARDWARE PACKAGE
Locate and check
contents. Screws
shown actual size.
Air deflector for
recirculating installation
49-80406
Printed in Italy 04-06 JR
36Hood
Template
8-1/2
Dia.
Cut a 1Dia.
Wire Access
Hole
Cut a 1Dia.
Wire Access
Hole
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
10-1/16to
Centerline
of Holes
7-1/16to
Centerline
of Holes
FRONT OF HOOD
7-1/16to
Centerline
of Holes
Template
6 ceiling
mounting
screws
42 screws total:
24 support frame
screws
10 hood attachment
screws
2 upper duct cover
attachment screws
4 recirculating
deflector screws
2 duct cover bracket
attachment screws
12 sheet
metal
screws
Decorative duct covers
(14"wide, 12-3/16" deep when assembled)
12 cage
nuts
8
Telescoping
support frame
Upper duct cover trim pieces
2 each of 4 sizes
1 charcoal filter for
recirculating installation
Stainless steel filter
24-3/4"
23-1/4"
2 Duct cover
brackets
2 thumb
screws
Lower duct cover trim pieces
Note: Some additional hardware/screws included.
9
Plan the Location of the Hood and Ductwork
Use a plumb bob to check the location. The
countertop/cooktop below the hood must be
centered with the hood.
The hood should extend beyond the front and rear
edge of the cooking appliance.
The duct in the ceiling must be centered over the
cooktop.
CONSTRUCT CEILING SUPPORT
Installation Preparation
Top view – ceiling joists parallel to front of hood
10-1/16"
Install cross-framing
symmetrically over
duct/cooktop
centerline
16" joist
spacing
7-1/16"
8” duct
Front
of
hood
2x4 cross
framing
Cooktop
outline
Align duct
to center of
cooktop
Ceiling Support Structure
At the hood location, install 2 x 4 cross framing
between ceiling joists as shown. (2x4’s are required to
support the weight of the hood.)
Arrange cross framing in the ceiling to suit the
existing structure.
Your ceiling joists will be like one of the following
examples.
EXAMPLE A
Ceiling
Hood
ducting
centerline
Cooktop
Countertop
Front
27-9/16"
13-3/4"
Side view
Align with
center of
cooktop
10
Top view – ceiling joists run perpendicular to front of hood
Top view – ceiling joists at angle to front of hood
Installation Preparation
CONSTRUCT CEILING SUPPORT
CONTINUED
10-1/16" install
cross-framing
symmetrically
over duct/cooktop
centerline
16" joist
spacing
7-1/16"
8" duct
Front
of
hood
2x4 cross
framing
Cooktop
outline
Align duct
to center
of cooktop
10-1/16" install cross-framing
symmetrically over duct/
cooktop centerline
16" joist
spacing
7-1/16"
8" duct
Front
of
hood
2x4 cross
framing
Cooktop
outline
Align duct
to center
of cooktop
EXAMPLE B
EXAMPLE C
Ceiling
Joist
10-3/4
2x 4
Mi
n.
Cross Framing
Height
Adjustment
Screw Holes
7-1/16"
11
CONSTRUCT CEILING SUPPORT
CONTINUED
Installation Preparation
Ductwork for Installations Vented to the Outdoors
Use the shortest and straightest duct route possible.
For satisfactory performance, duct run should not
exceed 100 feet equivalent length for any duct
configuration.
Refer to “Duct Fittings” chart to compute the
maximum permissible length for duct runs to the
outdoors.
This vent hood must use 8" round rigid duct.
Install the house ductwork to run horizontally
between ceiling joists or straight up through the
roof.
Finish the Ceiling
Finish the ceiling surface. Be sure to mark location
of the ceiling joists and cross framing. Check to be
sure the ceiling is level; use shims if necessary.
Ceiling Joint
2x4
10"
Duct
Vent Straight Up
Through The Ceiling
Secure each 2 x 4 block with at least four (4), #10
wood screws, 3" long (not supplied). Use 8 wood
screws total for the two supports.
The cross framing must be accurately aligned to
assure correct positioning of the hood.
The cross framing must be level in all directions.
Check with a spirit level and adjust if necessary.
IMPORTANT: The ceiling structure must be capable
of supporting the weight of the hood (approximately
200 pounds) and any inadvertent user contact loads.
The hood support frame will be supported by the
2 x 4 cross framing.
2 x 4 min.
cross framing
Ceiling
joist
7-1/16"
8"
Duct
Ceiling joist
2 x 4
Vent straight up
through the ceiling
10-1/16"
Height
adjustment
screws
12
Align the template with the marks on the ceiling
and tape in place.
Be sure the template is oriented correctly with the
front of the hood.
Use a plumb bob to be sure the mounting holes
will provide parallel alignment with the countertop
below.
• Center punch all hole locations.
Drill pilot holes in the 4 screw locations. Use a 3/16"
bit and drill approximately 1-1/2" deep.
Drive 4 hex head wood screws into the center of
the ceiling joists and cross framing. Leave a 1/4"
gap to allow the screw head to engage the keyhole
slots on the support frames.
• Cut the 8-1/2" duct opening through the sheet rock.
STEP 1 MOUNT TEMPLATE
Installation Instructions
STEP 2 ADJUST FRAME HEIGHT
•Measure exact ceiling height.
Find the exact frame height
required on the chart on page 6.
Remove 2 screws on each of the
4 sides of the frame to loosen the
upper structure, lower structure
and blower/motor.
Adjust the height “X”, according to
the chart on page 6. Use a total of
32 screws (8 screws on each side)
to secure the upper structure,
lower structure and blower/
motor together.
1/4" Gap
24"min.
30"max.
36"min.
Frame
height
2-3/4"
Ceiling
height
X
49-80406
Printed in Italy 04-06 JR
36Hood
Template
8-1/2
Dia.
Cut a 1Dia.
Wire Access
Hole
Cut a 1Dia.
Wire Access
Hole
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
10-1/16to
Centerline
of Holes
7-1/16to
Centerline
of Holes
FRONT OF HOOD
7-1/16to
Centerline
of Holes
,167$//$7,21³9(17('727+(2876,'(
13
Installation Instructions
STEP 3 CUT DUCT TO LENGTH FOR
VENTED INSTALLATION
Measure from
house duct to
exhaust opening.
Cut the 8" duct
length to size.
Slip duct over the
exhaust opening.
Seal the connection
with duct tape.
Duct
House
duct
Frame
height
Duct
length
STEP 4 INSTALL THE SUPPORT FRAME
Raise the support toward
the ceiling.
Thread the house wiring
through one of the large
holes, preferably on the
left side.
Carefully engage the
ceiling mounting screws
to the keyhole slots AND
the house duct in the top
of the frame.
Tighten the 4 mounting
screws against the frame.
Install 2 safety screws.
Use duct tape to seal the
duct connection at the top.
Duct
STEP 5 INSTALL HOOD ATTACHMENT
SCREWS
Install 4 hood attachment screws in the bottom of
the support as shown. Leave 1/4" gap between
screw head and support flange.
Safety
screws
Keyhole
slots
House
wiring
Keyhole
slots
Install 4
attachment
screws
,167$//$7,21³9(17('727+(2876,'(
14
STEP 7 CONNECT CABLES
Join the two cable connectors at the front of the
hood. Secure the cables behind the retainer clip.
Installation Instructions
STEP 6 MOUNT THE HOOD
ONTO THE SUPPORT
WARNING: Two people are required to
lift and position the hood onto the support.
AVERTISSEMENT : Il faut deux
personnes pour lever et mettre en place a hotte sur
le support de montage.
Lift the hood to the bottom of the support,
engaging the keyhole slots to the 4 mounting
screws.
• Tighten the 4 mounting screws.
• Install 6 additional screws as shown.
Install
6 screws
Retainer
clip
To
lights
To control
panel
,167$//$7,21³9(17('727+(2876,'(
15
Installation Instructions
STEP 8 CONNECT ELECTRICAL
Verify that power is turned off at the source.
WARNING: If house wiring is not 2-wire
with a ground wire, a ground must be provided by
the installer. When house wiring is aluminum, be sure
to use U.L. approved anti-oxidant compound and
aluminum-to-copper connectors.
AVERTISSEMENT :
Si la maison n’est pas câblee avec deux fils et un
fil de terre, l’installateur doit installer un fil de terre.
Quand les fils sont en aluminium, il faut prendre soin
d’utiliser des connecteurs aluminium à cuivre avec
une pâte antioxydante approuvée par U.L.
Remove junction box cover and knockout on the
left side.
Secure the house wiring to the junction box with
a strain relief.
Connect white leads to branch circuit white lead.
Connect black leads to branch circuit black lead.
Connect green/yellow leads to branch circuit green
lead or bare ground lead.
Secure all connections with wire nuts on each
electrical connector.
Push wires into junction box and replace cover.
Be sure wires are not pinched.
Secure J-Box cover with original screw.
Knockout
J-Box
cover
J-Box
cover
House wiring
,167$//$7,21³9(17('727+(2876,'(
16
Installation Instructions
STEP 9 PREPARE THE DUCT COVERS
Remove the plastic protective covering on all
duct pieces.
Install 3 cage nuts on each inside section of
the top duct cover. The cage nuts fit into the
rectangular slots, clips facing outward.
Install 3 cage nuts on each side of the lower
duct covers.
Support
frame
Plan
diagram
Rectangular
slots
Nut
STEP 10 INSTALL UPPER DUCT COVER
Place the tall duct covers onto the top of the
hood. This section has venting holes on one end.
NOTE: If you are installing this hood for
recirculating operation, place the duct covers
onto the hood with the venting slots at the top.
If the hood is vented to the outside, the holes
should be positioned on the bottom.
Secure the sides with 6 screws installed through
the cage nuts.
Raise the assembled duct covers to the top,
against the ceiling.
Match mounting holes, one on each side. Install
screws through the duct and into the support.
Top
sections
Top
sections
,167$//$7,21³9(17('727+(2876,'(
17
Installation Instructions
STEP 11 INSTALL LOWER DUCT COVER
Place rear duct cover onto the hood.
Place front duct cover onto the hood.
Secure the duct covers with 6 screws.
Front bottom duct cover section
(snap into place and secure
with 6 screws – 3 per side)
Plan diagram
top view
Front bottom duct
cover sections
STEP 12 INSTALL DUCT COVER TRIM
Install side brackets to secure the lower duct
tightly against the upper duct.
Hold lower trim strips (narrow pieces) with hooks
facing down. Place the hooks inside the slots and
slide downward.
Select the correct size upper trim strips and press
into place.
Upper
trim
strip
Lower
trim strip
Lower
trim
strip
Upper
trim
strip
Side
bracket
,167$//$7,21³9(17('727+(2876,'(
STEP 13 INSTALL METAL FILTER
IMPORTANT: Check to be sure that the main ON/
OFF switch next to the motor is in the ON
position.
Tip the filter into the left or right side of the
opening. Lift the filter to the opposite side and
into the filter lock.
To remove the filter, pull the filter lock downward.
Filter lock
STEP 14 FINALIZE INSTALLATION
Remove all tape and packing material.
Refer to the Owner’s Manual for operating instructions.
18
Installation Instructions
Align the template with the marks on the ceiling
and tape in place.
– Be sure the template is oriented correctly
with the front of the hood.
Use a plumb bob to be sure the mounting holes
will provide parallel alignment with the countertop
below.
• Center punch all hole locations.
Drill pilot holes in the 4 screw locations. Use a 3/16"
bit and drill approximately 1-1/2" deep.
Drive 4 hex head wood screws into the center of
the ceiling joists and cross framing. Leave a 1/4"
gap to allow the screw head to engage the keyhole
slots on the support frames.
STEP 1 MOUNT TEMPLATE
STEP 2 ADJUST FRAME HEIGHT
•Measure exact ceiling height.
Find the exact frame height
required on the chart on page 6.
Place the support on a work
surface. Remove 2 screws on
each of the 4 sides of the frame
to loosen the upper structure,
lower structure and blower/
motor.
Adjust the height “X”, according
to the chart on page 6.
Use a marker pen to indicate
where screw holes should align
in the assembled upper, lower
and blower/motor pieces.
1/4" Gap
24"min.
30"max.
36"min.
Frame
height
2-3/4"
Ceiling
height
X
49-80406
Printed in Italy 04-06 JR
36Hood
Template
8-1/2
Dia.
Cut a 1Dia.
Wire Access
Hole
Cut a 1Dia.
Wire Access
Hole
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
Drill 3/16
Pilot Holes
Approx. 1-1/2
Deep
10-1/16to
Centerline
of Holes
7-1/16to
Centerline
of Holes
FRONT OF HOOD
7-1/16to
Centerline
of Holes
,167$//$7,21³5(&,5&8/$7,1*
NOTE: Do not cut the
duct opening shown
on the template for
this recirculating
installation.
NOTE: Low ceilings may require that
the lower portion of the support frame be
removed. The upper support frame may be
secured directly to the blower/motor. Refer
to the chart on page 6 for your ceiling
height and to be sure the duct cover trim
piece will fit.
Mark
each
piece to
indicate
where
screw
holes
align.
19
Installation Instructions
STEP 4 INSTALL UPPER SUPPORT FRAME
Raise the upper support
toward the ceiling.
Thread the house wiring
through one of the large
holes, preferably on the
left side.
Carefully engage the
ceiling mounting screws
to the keyhole slots in
the top of the frame.
Tighten the 4 mounting
screws against the frame.
Install 2 safety screws.
Slide air deflector into
the support frame.
Secure the deflector
to the support with
4 screws.
Install the duct
piece to the
bottom of the
deflector and seal
the connection
with duct tape.
Safety
screws
Keyhole
slots
House
wiring
Keyhole
slots
,167$//$7,21³5(&,5&8/$7,1*
STEP 3 INSTALL AIR DEFLECTOR,
CUT DUCT FOR RECIRCULATING
OPERATION
FRONT
Temporarily, slide the
air deflector into the
support frame.
FRONT
Measure duct length
between the deflector and
over the exhaust opening.
Cut duct piece to length
and set aside.
Duct
length
20
STEP 5 INSTALL LOWER STRUCTURE
TO UPPER STRUCTURE
Slide lower frame into
the upper frame. Match
the marked alignment
holes.
Secure the upper and
lower frame with 16
screws, 4 on each side
of the frame.
Installation Instructions
,167$//$7,21³5(&,5&8/$7,1*
STEP 6 INSTALL BLOWER/MOTOR
Raise the blower/
motor piece toward the
assembled frame.
Carefully raise the motor
to the marked reference
point while making sure
the duct piece slips over
the blower outlet flange.
Secure the blower/motor
to the frame using 16
screws, 4 on each side.
Use tape to seal the duct
connection.
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28

Monogram GEZV925SLSS Guide d'installation

Catégorie
Hottes
Taper
Guide d'installation
Ce manuel convient également à

dans d''autres langues