Installation Environment Required:
The lift shall work indoor where there is no any corrosive or combustible substance; and should not approach the
steam pipe, hot air pipe, or other central heating equipment.
1. Voltage: 110-120 V or 220-240V, Power: 60W
2. Max Tilt angle ≤1°
Max Roll angle ≤3°
Installation:
1, The distance between ceiling and false ceiling must bigger than the height of fold up size(L1) of the lift..
2, Suggest open dimension on false ceiling for the lift is :460mmX460mm
3, Suggest open a 400mmX400mm maintenance window on the false ceiling, 100mm~200mm away from the back side of
the lift.
4, Drill four holes correctly on the ceiling for the installation plate, considering the direction of the installed projector, then
mount the installation plate of the lift on the ceiling firmly with four ∅8mm explosion screws through the four ∅10mm
screw holes.
5, The explosion screws must installed in concrete or masonry or more strong ceiling. The explosion screws must drill deeply
into the ceiling to keep adequate bearing capability.
Notice:
1. The explosion screws must fixed on the ceiling firmly.
2. While the lift working, people must not stand below the lift, or locate anything at the level where it can reach.
3. Make sure the gravity of the projector in the center of the lift, or the center of the gravity will shift or loss balance;
And the lift can’t work overloaded.
4. Please do not put your hands or anything to the cross-scissor parts while the lift working to avoid injury.;
Trouble shootings:
Please let technicians check below items, if still can’t solve the problems, please contact the resellers.
1. Please check if the connection of the power cord is correct.
2. Please check if the strip is entangled or loose.
3. Please check if the E-Stop button is pressed down.
4. Please check if the limit switch is loose or shift .
Accessories for CPL Standard Model:
Accessories for CPL Economic Model:
2
Central control Cable
Adapter(x1)
12V Trigger cabie elw
Screw rod X4
L=100mm
RF Transmitter
X1
L=100mm